Report
available from Yggdrasil,
P.O. Box 910476, Lexington, KY
40591-0476 for
$12 including postage. Checks should be made out to Yggdrasil/Earth
Island.
Excerpts from:
The US Uranium Enrichment Establishment, 1999
By Mary Byrd Davis
Published by the Uranium Enrichment Project of Earth Island’s
Yggdrasil, August 9, 1999
Introduction
The US Uranium Enrichment Establishment is designed to serve
as a reference tool, presenting the basic facts about the establishment
woven into a coherent whole. Our aim is to enable readers to better
understand, follow, and, to the extent possible, influence developments
in the industry and at the enrichment plants. It is not an investigative
report. Much of our information comes from official sources. We hope,
however, that the report will give people wanting to examine in depth
particular aspects of the industry a starting point for their research
and a framework within which to work.
The report opens with background information on the process of
uranium enrichment and the history of uranium enrichment in the United
States. It then presents the roles of the major companies and agencies
involved with the enrichment establishment starting with the United
States Enrichment Corporation (USEC), created in 1993 and privatized in
1998, and the agency that now regulates enrichment operations, the US
Nuclear Regulatory Commission. It outlines operations and facilities at
the Paducah, Kentucky, and Portsmouth, Ohio, gaseous diffusion plants,
the only two US plants that enrich uranium today, and notes major
buildings at a third gaseous diffusion plant, located at Oak Ridge,
Tennessee, which is no longer in operation. It then looks at USEC, or as
appropriate, USEC and the US Department of Energy (DOE), in terms of a
series of concerns: plant safety, national security, social issues, and
the environment.
In regard to plant safety, the report notes that a fire in December
1998 in a process building at Portsmouth demonstrated weaknesses in
emergency preparedness, and that at Paducah, which has operated with
less down time because of equipment failures and incidents than has
Portsmouth, earthquakes pose a threat that USEC has still not adequately
countered. In terms of national security, the report shows that USEC
plays a major role as US executive agent of the Russian HEU agreement
but that the company has always been a somewhat reluctant player. Social
issues are treated in terms of jobs and health. For workers at the
plants, the possibility of layoffs has been a pressing matter ever since
the US Congress began preparing the way for the privatization of
enrichment operations, but massive cutbacks have not yet occurred;
equally pressing for many former workers and for area residents is the
question of the impacts of the plants on health, a question never
adequately addressed. In our section on the environment, DOE is the main
subject, since the agency, which owns and once ran the three gaseous
diffusion plants, is responsible for cleaning up contamination and
disposing of waste produced prior to 1993 and for decommissioning the
facilities. DOE’s handling of contaminated scrap metal at the former
K-25 plant at Oak Ridge, now known as the East Tennessee Technology
Park, is setting a frightening precedent for the eventual
decontamination and decommissioning of the Paducah and Portsmouth
plants. Release of the metal is spreading radioactive material outside
the plants, a situation that appears likely to repeat itself in regard
to management of the massive amounts of depleted uranium hexafluoride, a
byproduct of the enrichment process, stored at the enrichment sites.
The report closes with a look at uranium enrichment in terms of
finances. USEC ended its 1999 fiscal year, June 30, 1999, on an upbeat
note, as its revenue for FY 99 exceeded that for FY 98 despite a dim
showing in the third quarter of FY 99. One of the reasons for the upturn
was USEC’s indefinite suspension of plans to build a facility that
would enrich uranium by the Atomic Vapor Laser Isotope Separation (AVLIS)
process. AVLIS has never been deployed on the commercial level, and its
abandonment appears to have been wise. However, USEC has yet to find the
means of remaining profitable in future decades. Reliance on facilities
almost fifty years old that devour electricity will not allow it to stay
competitive indefinitely in the tight enrichment market.
In a sense, this report is a work in progress. The subject is vast,
and the situation within the enrichment establishment is constantly
changing. We hope to continue our monitoring and would welcome comments
and observations on this presentation.
USEC in Relation to Plant Safety
In September, 1998, Public Citizen and the Union of Concerned
Scientists accused the NRC of concealing problems at the Paducah and
Portsmouth plants in order to expedite the initial offering of stock to
the public. They called on the Justice Department and the Securities and
Exchange Commission to “‘immediately commence an investigation of
this government-business coverup.’” According to Ralph Nader, the
NRC brushed aside, in the weeks before and after the sale, a series of
safety shortcomings listed in one of its own internal memos. The NRC and
USEC denied the charges, stating that problems at the plants had been
publicly aired.
The NRC underlined the need for safe management of the plants when it
insisted that USEC pay an annual certification fee greater than that
regularly applied to facilities with low-enriched uranium. It explained
that gaseous diffusion plants “are subject to a relatively large
number of credible accidents most of which have multiple initiating
events. The potential on-site and off-site consequences posed by these
accidents are significantly greater than those applicable to
low-enriched uranium facilities.”
The NRC’s reports to Congress summarize the status of the plants
from the point of view of the agency.
Event Reports
The most serious “event” at the two plants since the NRC took
over regulation occurred December 9, 1998, and thus will appear in the
third annual report to Congress. On that date a fire largely destroyed a
cell in a side purge cascade in process building, X-326, at Portsmouth.
USEC hypothesizes that the fire resulted when an aluminum component
of the process equipment became so hot that it initiated an
aluminum/uranium hexafluoride reaction. Such a reaction is highly
exothermic. NRC’s augmented inspection team (AIT) agreed with USEC’s
evaluation of the cause but were critical of what the fire showed about
firefighter training and emergency planning, and of some of the
post-fire procedures at Portsmouth. For instance, the operations staff
did not cut off the oil supply to the burning cell, emergency personnel
failed to communicate the severity of the fire to management, and the
plant did not properly inform government authorities of the accident.
USEC reported to the US EPA that radioactive material was released
through the vents/stacks in the X-326 building and through fugitive
emissions caused by the fire’s breaching the process piping and cell
housing. In the latter case the radionuclides were released into the
process building; subsequently an unknown quantity escaped to the
atmosphere through roof ventilators. The interior metal surfaces in the
side purge cascade where the fire took place were contaminated with
technetium. Apparently the fire heated metal surfaces within the side
purge cascade sufficiently to vaporize technetium that was sticking to
them. “The chemical traps on the process vents became saturated and
technetium was emitted to the atmosphere.”
A Lockheed Martin memo of January 6, 1999, states that an estimated
16.6 pounds of UF6 were released during the fire and that the estimated
uranium to technetium ration was apparently between 0.4:1 and 0.17:1. .
.
June 30, 1999 the NRC announced that it had proposed a $55,000 fine
against USEC for failing to declare an alert under its emergency plan
during the fire.
Performance
Both reports to Congress begin their sections on performance, with
reservations about the condition of the plants. “The GDPs at Paducah
and Portsmouth are more than 40 years old… They were built at a time
when design standards and quality assurance standards were significantly
different from current requirements, and documentation requirements were
less stringent. The age of the facilities, some poor documentation of
design and safety bases, and the requirements in effect when the plants
were constructed have resulted in difficulties in maintaining the
physical condition of the facilities. These shortcomings have challenged
USEC’s performance during the period; however, both the material
condition of the plants and the design and safety basis documentation
are being upgraded.”
The 1997 report states that operational performance at both plants is
“acceptable” but needs further improvement. USEC needs to increase
its understanding of “the required level of performance and
operational rigor,” among other things. The 1998 report distinguishes
between the two plants. At Paducah overall performance was “adequate
and continued to improve.” “However… plant staff training
continues to be an area requiring improvement.” Early in the second
review period, the NRC noted a decline “in the rigor and quality of
some engineering analysis, “ but that decline was stemmed. The
evaluation of Portsmouth was harsher.
At Portsmouth, overall performance was “adequate” and the conduct
of plant operations “acceptable,” but “consistent implementation
of Technical Safety Requirements, adherence to plant policies and
procedures, and communications across plant organizations were areas in
which improvements continued to be warranted.” . .
Completion of Compliance Plan Commitments
NRC indicated in its second annual report to Congress that USEC had
completed or was scheduled to complete by the end of 1998 all Compliance
Plan commitments for issues common to both plants, except Autoclave
Upgrades scheduled to be complete by January 2, 1901, and Procedures
Program, scheduled to be complete by March 3, 2002. Only three items
awaited completion by the end of 1998. All issues specific to Portsmouth
had been completed, except the removal of uranium enriched to greater
than 10% uranium 235, which was to be resolved by January 31, 1999. All
issues specific to Paducah had been completed, except the improvements
in Seismic Capability of buildings C-331 and C-335. The last is not a
minor matter.
Earthquake Risk
The compliance plan to which USEC committed itself in November 1996
when the NRC granted the gaseous diffusion plants certificates of
compliance required USEC to improve seismic safeguards in two buildings
of the Paducah plants by December 31, 1997. The buildings were the C-331
and C-335 process buildings, which are similar to one another. The
following year USEC asked for a delay in implementing the upgrades on
the grounds that a delay would allow the NRC staff to review “new
information...[that] calls into question the need for and effectiveness
of the planned seismic upgrades.” The NRC moved the date for
completion to June 30, 1999.
The agency recapitulated its position in the Compliance Plan section
of the Compliance Evaluation Report for The Renewal of Certificate of
Compliance GDP-1, issued in January 1999. “During the SAR upgrade
project, DOE identified structural weaknesses in two of the main process
buildings. Structural seismic loading capacity analyses indicated that
significant structural damage could occur at peak ground acceleration
levels...above 0.05 g. Buildings C-331 and C-335 were the affected
buildings. At peak ground acceleration levels above 0.05 g, buildings
C-331 and C-335 would suffer collapse of 20-foot wide sections of the
roof and all four levels above ground. These sections traverse each
building in three places. USEC is to modify buildings to strengthen
building structures and increase the seismic capacity of the floor and
roof sections to withstand a 0.16 g seismic event. The modifications are
to be complete by June 30, 1999. The original completion date was
December 31, 1997.”
Nevertheless, USEC is now seeking a further extension. According to
Nuclear Fuel, Steven Toelle, USEC regulatory policy manager, wrote
December 15, 1998 to NRC’s Robert Pearson, that the seismic
modifications to C-331 and C-335 have “proven to be substantially more
difficult than originally anticipated.” These problems, “coupled
with the reduced worker productivity experienced in the high heat
conditions of the process buildings, are projected to more than double
the original estimated cost of the project and will result in a delay of
approximately 12 months in the overall construction schedule.” USEC is
asking that the compliance date be June 30, 2000. The original cost of
the modifications was estimated to be $23 million, according to USEC’s
Elizabeth Stuckle. USEC sent its desired change in the compliance plan
to DOE December 11, 1998. After the company received DOE approval, it
requested a delay from the NRC.2 The NRC posted a notice in the Federal
Register of June 17, 1999, stating that it had received an amendment
application from USEC and that it would receive comments for thirty
days. Thus, the deadline for completion of the seismic upgrades passed
before the NRC decided whether to extend the time limit.
Meanwhile, USEC has completed seismic modifications to equipment in
buildings C-310 and C-315. These modifications were not part of the
original Compliance Plan (the buildings’ accumulators, which contain
UF6 and could have failed at a seismic level of 0.05g had been
overlooked because their capacity was incorrectly reported in the
site’s SAR). The equipment was the subject of a Confirmatory Order
Modifying Certificate in April 1998. The accumulators and other items
have now been strengthened to withstand an acceleration of 0.165g.
DOE and USEC in Relation to the Environment
. . . . Special Concerns
Radioactive scrap metal and depleted uranium are found in enormous
quantities at the gaseous diffusion plants. If DOE goes ahead with
current plans, products made from both materials are likely to be widely
used outside of nuclear plants.
Scrap Metal
The NRC is in the process of making a rule concerning management of
“materials and equipment having residual radioactivity ,” and has
already determined that the rule will permit release and reuse of these
materials. A memorandum of June 30, 1998, from John C. Hoyle, Secretary
of the Commission, to L. Joseph Callan, Executive Director for
Operations, stated “The rulemaking should focus on the codified
clearance levels above background for unrestricted use that are
adequately protective of public health and safety. This level should be
based on realistic scenarios of health effects from low doses that still
allows quantities of materials to be released. The rule should be
comprehensive and apply to all metals, equipment, and materials,
including soil. If problems that would delay completing the rulemaking
arise in certain categories of solid materials, then a decision can be
made to narrow the scope of the rule.” (italics added; underlining in
source)
The EPA, after taking tentative steps towards establishing a standard
for release of slightly contaminated materials, has in effect handed the
issue over to the NRC. Under the leadership of the NRC, an Interagency
Steering Committee on Radiation Standards met June 10, 1999.
“Facilitated public meetings” on NRC’s rulemaking will be held in
Chicago, Atlanta, San Francisco, and Washington, DC in late summer and
fall of 1999. The deadline for comments from the public is November 15,
1999. Meanwhile, DOE is quietly releasing radioactive metal on a case by
case basis from sites across the country. The metal goes to metal
processing facilities and then to manufacturers of products, without any
warning label. Consumers who buy contaminated items will not know the
suspect origin of the metal in their purchases. Items made from
radioactive metal may be freely melted down and the metal reused.
DOE has selected Oak Ridge as the lead site for its National Scrap
Metal Reuse/Recycle Program. Oak Ridge is thus, DOE says, to “play a
major role in reducing waste dispositioning costs across the DOE
complex. Commitment by other DOE sites to supply scrap metal and use the
finished products is the key to the success of the program.”1
Presumably most, if not all, scrap metal from Portsmouth and Paducah
deemed to be recyclable will be sent to Oak Ridge for handling. The Oak
Ridge-based program was in 1997 “developing a business plan to
identify opportunities and commitments at other sites.” It intended to
“establish commitments” in 1998 and 1999.
August 25, 1997, DOE entered into a $284 million, six-year,
noncompetitive contract with British Nuclear Fuels Ltd. (BNFL) for the
decommissioning of the K-29, K-31, and K-33 process buildings at ETTP.
In the words of CROET, the company will “clean up” the buildings
“for eventual industrial use, plus recycle a vast majority of the
valuable material recovered from the buildings for reuse. This is a
first-of-a-kind contract to decontaminate and decommission U.S. gaseous
diffusion plants.” That it is the first means that it sets a dangerous
precedent.
By the terms of the contract BNFL receives title to radioactive metal
within the buildings and can remove from the buildings and sell for
profit up to an estimated 126,000 tons of radioactive nickel, aluminum,
copper, and steel scrap. BNFL will subcontract for disposition of the
metal with its subsidiary the metal smelter Manufacturing Sciences
Corporation (MSC), which is licensed by the state of Tennessee.
Tennessee regulators will therefore determine up to what level of
radiation, material can be released and reused. The contract put no
limitations on end use. Thus the metal will be able to be melted down
and used in consumer products. Possible uses range from cookware,
through children’s gym sets, to dental braces. On March 26, 1999, the
Tennessee Department of Environmental Conservation (TDEC) approved,
without public input, an amendment to the license of Manufacturing
Sciences Corporation allowing it to release nickel from the uranium
enrichment cascades that has volumetric contamination, i.e.
radioactivity throughout rather than only on the surface.
The Oil, Chemical, and Atomic Workers Union (OCAW; now PACE), the
Nuclear Information and Resource Service (NIRS), and various other
organizations sued DOE and BNFL under the National Environmental Policy
Act. They asked for a full environmental review before execution of the
cleanup. Judge Gladys Kessler ruled for the government, June 30, 1999.
She agreed with DOE that BNFL’s plan to sell metal for reuse was “an
integral part of the overall project under Superfund” and “not
subject” to a separate review under NEPA, but she noted that there is
“ample evidence that the proposed recycling significantly affects the
quality of human environment.”
The Green Scissors campaign, sponsored by Friends of the Earth,
Taxpayers for Common Sense, and the U.S. Public Interest Research Group
and supported by a wide variety of consumer, health, and environmental
organizations called on DOE to cancel the contract with BNFL, saying
that cancellation would save taxpayers $251.6 million over the remaining
years of the contract, that leaving the buildings in their current state
does not “pose a high-priority health and safety risk compared with
the rest of the Oak Ridge site,” and that retaining the contract will
result in production of consumer goods that will cause “continuous,
routine and unwitting exposure to radioactivity.”
This report was made possible by financial support from The John
Merck Fund.
copyright © 1999 by Yggdrasil
Home
| France Nucléaire | News
Primal Nature
| Green
Tourism |
Donate
|
comments, suggestions, &
technical matters contact: |
|